Great question! Let's break this down. The core goal is to make sure Stage C locks in a node first before Stages A and B can claim available resources—this way, we keep the total runtime capped at 4 hours (since A and B finish within C's 4-hour window) instead of letting A/B start first and pushing total time to 6 hours. Here are two solid approaches:
Approach 1: Use Stage Priority (Requires Pipeline: Job Plugin)
If you have the Pipeline: Job Plugin (version 2.28 or newer) installed, you can directly set priority levels for individual stages in your parallel block. This tells Jenkins to prioritize scheduling Stage C over A and B whenever a node becomes available.
pipeline { agent none stages { stage('Parallel Execution') { parallel { stage('Stage C') { // Set highest priority for C options { priority(10) } agent { node { label 'your-worker-nodes' } } steps { echo "Starting Stage C (4-hour task) first!" sh "sleep 14400" // Simulate 4-hour workload } } stage('Stage A') { // Lower priority for A options { priority(1) } agent { node { label 'your-worker-nodes' } } steps { echo "Starting Stage A (2-hour task)" sh "sleep 7200" // Simulate 2-hour workload } } stage('Stage B') { // Lower priority for B options { priority(1) } agent { node { label 'your-worker-nodes' } } steps { echo "Starting Stage B (2-hour task)" sh "sleep 7200" // Simulate 2-hour workload } } } } } }
Why this works:
Jenkins will prioritize scheduling the high-priority Stage C first. Once C takes one node, the second node will go to either A or B. When that first short-running stage finishes, the freed node will take the remaining stage—all within the 4-hour window of Stage C.
Approach 2: Scripted Node Preemption (No Plugins Needed)
If you can't use plugins, you can embed a scripted pipeline snippet inside your declarative pipeline to explicitly start Stage C first, ensuring it grabs a node before A and B are scheduled.
pipeline { agent none stages { stage('Parallel Execution with C Priority') { steps { script { // Define Stage C first to grab a node immediately def runStageC = { node('your-worker-nodes') { echo "Preempting node for Stage C (4-hour task)!" sh "sleep 14400" // Simulate 4-hour workload } } // Define Stages A and B def runStageA = { node('your-worker-nodes') { echo "Starting Stage A (2-hour task)" sh "sleep 7200" // Simulate 2-hour workload } } def runStageB = { node('your-worker-nodes') { echo "Starting Stage B (2-hour task)" sh "sleep 7200" // Simulate 2-hour workload } } // Launch Stage C first, then parallelize A and B def cFuture = runStageC.start() parallel(runStageA, runStageB) // Wait for Stage C to finish before marking the pipeline complete cFuture.join() } } } } }
Why this works:
By explicitly starting Stage C first with start(), we force it to claim a node right away. We then launch A and B in parallel—they'll take the second available node, and the remaining one will run once the first short stage finishes. Since all three stages run concurrently (C runs the full 4 hours, A/B finish in 2), total runtime stays at 4 hours.