如何根据任务起止日期与TODAY()函数计算任务预期完成百分比?

Calculating Expected Task Completion Percentage with Start/End Dates & TODAY()

Hey there, let's break down exactly how to calculate the expected completion percentage for a task using its start date, end date, and the TODAY() function. This is a super common need for project trackers or spreadsheets, so I'll cover all the key scenarios and edge cases to make sure you've got it right.

Core Variables First

Let's define the values we're working with to keep things clear:

  • Start_Date: The official start date of your task
  • End_Date: The scheduled end date of your task
  • Today_Date: The current date, pulled dynamically via the TODAY() function

Scenario 1: Task hasn't started yet

If today's date is before the task's start date, the task hasn't begun—so completion percentage is 0%.
The check for this looks like:

IF(TODAY() < Start_Date, 0, ...)

Scenario 2: Task is already completed

If today's date is on or after the task's end date, the task should be fully done—so completion percentage is 100%.
The check here is:

IF(TODAY() >= End_Date, 100, ...)

Scenario 3: Task is in progress (active period)

This is the core calculation. We need to find what percentage of the total task duration has passed as of today.

Key Note About Date Math

When you subtract dates (e.g., End_Date - Start_Date), you get the number of days between those dates—not the total number of days the task spans. To fix this, we add 1 to include both the start and end dates in the count.

The formula for in-progress completion is:

ROUND(((TODAY() - Start_Date + 1) / (End_Date - Start_Date + 1)) * 100, 2)
  • TODAY() - Start_Date + 1: Number of days completed so far (including today)
  • End_Date - Start_Date + 1: Total scheduled days for the task
  • Multiply by 100 to get a percentage, use ROUND() to keep it clean (2 decimal places here)

Full Combined Formula

Putting all scenarios together (plus a check for invalid date ranges, like start date being later than end date):

=IF(Start_Date > End_Date, "Invalid Date Range", 
    IF(TODAY() < Start_Date, 0, 
        IF(TODAY() >= End_Date, 100, 
            ROUND(((TODAY() - Start_Date + 1) / (End_Date - Start_Date + 1)) * 100, 2)
        )
    )
)

Quick Examples to Verify

Let's test with real dates to make it concrete:

  • Example 1: Start=2024-05-01, End=2024-05-10, Today=2024-05-03
    Total days: 10-1+1=10 | Days completed:3-1+1=3 | Completion: (3/10)*100 = 30%
  • Example 2: Today=2024-04-28 (before start date) → 0%
  • Example 3: Today=2024-05-15 (after end date) → 100%