Calculate Execution Duration for Stepping Thread Group (Mathematical Formula)

I've translated your Java code logic into a set of mathematical formulas so you can compute the total execution duration of a Stepping Thread Group directly, without relying on code loops. Let's break this down step by step:

First, let's define all the input parameters (matching your code variables):

  • TotalThreads: Total number of threads to run
  • firstWait: Initial wait time before starting any threads (seconds)
  • thenStart_threads: Number of threads launched in the first batch
  • nextAdd_threads: Number of threads added in each subsequent batch
  • threadsEverySeconds: Interval between starting subsequent thread batches (seconds)
  • usingRamupSeconds: Ramp-up time to launch a batch of threads (seconds)
  • holdForSeconds: Duration to run all threads at full capacity (seconds)
  • finallyStopThreads: Number of threads stopped in each batch during ramp-down
  • down_threadsEverySeconds: Interval between stopping subsequent thread batches (seconds)

1. Ramp-Up Phase Duration

This covers the time from initial wait to launching all threads. We split this into two scenarios based on whether you have an initial thread batch:

Scenario 1: thenStart_threads > 0

  1. Initial batch setup: Time to wait, launch the first batch, and wait for the next interval:
    initial_ramp = firstWait + usingRamupSeconds + threadsEverySeconds
    
  2. Remaining threads to launch:
    RemainingThreads = TotalThreads - thenStart_threads
    
  3. Calculate full batches and final partial batch:
    • Number of complete batches of nextAdd_threads threads:
      full_batches = floor( (RemainingThreads - 1) / nextAdd_threads )
      
      (We subtract 1 to ensure the final full batch doesn't include an extra interval)
    • Threads in the final (possibly partial) batch:
      final_batch_threads = RemainingThreads - (full_batches * nextAdd_threads)
      
  4. Time for remaining batches:
    • Time for all full batches (each includes ramp-up + interval):
      full_batches_time = full_batches * (usingRamupSeconds + threadsEverySeconds)
      
    • Time for the final batch:
      final_batch_time = if final_batch_threads == nextAdd_threads 
                         then usingRamupSeconds 
                         else (final_batch_threads / nextAdd_threads) * usingRamupSeconds
      
  5. Total ramp-up time:
    rampupTime = initial_ramp + full_batches_time + final_batch_time
    

Scenario 2: thenStart_threads = 0

Skip the initial batch setup, start with the initial wait time, then calculate remaining batches the same way:

rampupTime = firstWait + full_batches_time + final_batch_time

(Use the same RemainingThreads = TotalThreads, full_batches, and final_batch_time calculations as above)


2. Ramp-Down Phase Duration

This covers the time to stop all threads after the hold phase. The logic is: we stop finallyStopThreads threads each interval, and don't need an interval after the final stop:

RampDown = ( (TotalThreads // finallyStopThreads) - 1 ) * down_threadsEverySeconds

(The // denotes integer division, matching your Java code's behavior)


3. Total Execution Duration

Add up all three phases to get the total runtime:

TotalDuration = rampupTime + holdForSeconds + RampDown

Example Validation (Using Your Code's Parameters)

Let's test with your sample values:

TotalThreads=500, firstWait=25, thenStart_threads=5, nextAdd_threads=25, threadsEverySeconds=30, usingRamupSeconds=5, holdForSeconds=600, finallyStopThreads=25, down_threadsEverySeconds=25
  1. RemainingThreads = 500 - 5 = 495
  2. full_batches = floor( (495-1)/25 ) = 19
  3. final_batch_threads = 495 - (19*25) = 20
  4. final_batch_time = (20/25)*5 = 4
  5. initial_ramp = 25 +5 +30 = 60
  6. full_batches_time =19*(5+30)= 665
  7. rampupTime=60+665+4=729
  8. RampDown=(500//25 -1)*25= (20-1)*25=475
  9. TotalDuration=729+600+475=1804

This matches the output from your Java code perfectly, confirming the formulas work.